Maintenance injection mold program A. Inspection and ma […]
Maintenance injection mold program
A. Inspection and maintenance during mold installation
1. Before installing the mold, clean the upper and lower surfaces of the injection mold to ensure that the installation surface of the injection mold matches the press table correctly.
2. After the mold is installed, open the mold, clean the guide mechanism and the surface of the cavity to ensure the quality of the parts.
3. Lubricate or lubricate the sliding parts of the mold.
4. Check and maintain the side guards, clean the waste grooves and punch holes.
5. Check the mold side pins, screws, etc., and repair and replace them in time if any problems are found.
B. Maintenance in production
In production, we often observe and feel the use of the mold. If any abnormality is found, it should be stopped immediately for inspection and eliminated in time. After troubleshooting, production can proceed.
C. Post-production maintenance
1. After the production is over, check the injection Helmet Mould.
2. Clean the injection mold, clean up the waste and sundries in the mold, and ensure that there is no waste in the waste box.
3. Feed back the problems found in the use of the injection mold truthfully, and make a record on the handover list or notify the maintenance personnel for maintenance.
4. Long-term maintenance of injection molds
For long-term injection molds, maintenance should be scheduled every two months. The method is to open the injection mold to remove dust and rust, and oil all parts of the injection mold